Job Reports

Stokes Hill Wharf Fender Piles

photo1

Muller MS32 HFV Crane suspended vibro and  BSP CX110 Impact hammer ThyssenKrupp Steelcom supplied both our Muller MS32HFV vibro and BSP CX110 impact hammer to Advance Civil and Engineering to install 22 x 32m long fender piles on their Stokes Hill Wharf upgrade. The piles were set with the vibro and back driven with the impact […]

read more...

East Arm Port Stabilisation

EastArmPort

Equipment used ABI 14/18 Piling Rig, fitted with ABI MRZV 24VV Vibro hammer Muller MS7 Vibro STU 1800 Sheetpile Macalloy tie bars and fittings ThyssenKrupp Steelcom provided installation equipment and sheetpile to the Barclay Mowlem Thiess Joint Venture for rectification works on the Port loading/unloading facility located at East Arm Darwin NT. The project included […]

read more...

Darwin Marine Supply Base

2013-12-10 14.50.12_2

Equipment used ABI 14/18 Piling Rig, fitted with ABI MRZV 24VV Vibro hammer ThyssenKrupp Steelcom provided installation equipment and sheetpile to Teras Australia for the upgrade of their Marine barge terminal located at East Arm Darwin NT. The project included 387 x sheets of Larssen L720 sheetpile at a length of 10m, for the construction […]

read more...

ABI HVR 60 Vibrohammer Sold to Black Widow

IMG_0669

ThyssenKrupp Steelcom has recently sold its ABI HVR 60 to Black Widow Civil, one of the prominent contractors based in the Gold Coast, QLD area. Black Widow Civil is currently using the ABI HVR 60 on a Gold Coast light rail project taking place in Southport, QLD. The full job report is available. To find […]

read more...

Vibro Hammers Job Report – Newcastle

Vibro Hammers - Newcastle

Newcastle New South Wales Ferry Wharf Construction Contractor Newcastle Wharf and Jetty Repairs used our 50HL hammer to drive 21.7 metre long steel tubes that were 900mm diameter with a wall thickness of 16mm. The pile verticality was between 8 and 25mm over a 4 metre distance which was within the 1:150 required. The 50HL […]

read more...

Vibro Hammers Job Report – Auckland

Vibro Hammers - Auckland

Auckland New Zealand Wharf Construction Fletcher Construction used Steelcom’s 50HL hammer in the construction of wharves at Marsden Point, 150km north of Auckland. Fletcher drove 25m casings 1219mm in diameter with a wall thickness of 9.5mm plus 30m casings 914mm in diameter with a wall thickness of 12.5mm.

read more...

Vibro Hammers Job Report – Canterbury

Vibro Hammers - Cantebury

Canterbury New Zealand Foundation Construction For this ICT project, pile foundation columns were created and the PTC30H1 Vibro Hammer was used to drive 900mm dia casing down 15m. The site was excavated, the casings driven down, then drilled out to check bottom of the casing for solid ground, thereafter a steel cage was laid and […]

read more...

Vibro Hammers Job Report – Raymond Terrace

Vibro Hammers - Raymond Terrace

Raymond Terrace New South Wales Abutment Reinforcement Contractor Civilbuild is seen here using our 15HF3 to drive 8 metre LX16 sheet pile into stiff clay for an abutment reinforcement. The 15HF3 is a high frequency hammer that limits vibration emissions, making it possible to operate in city areas. The 15HF3 is able to drive and […]

read more...

Vibro Hammers Job Report – Groote Eylandt

Vibro Hammers - Groote Eylandt

Groote Eylandt 600km east of Darwin Barge wharf extension NT contractor Transcon (Trans Australian Construction) recently completed the extension of a barge wharf on Groote Eylandt commissioned by BHP Billiton subsidiary GEMCo (Groote Eylandt Mining Company). The wharf extension is 8 metres x 19 metres with a protective weather wall 15 metres long at 45 […]

read more...

Vibro Hammers Job Report – Coffs Harbour

Vibro Hammers - Coffs Harbour

Coffs Harbour Northern New South Wales Deep sea release, cofferdam construction Barclay Mowlem Candac in alliance with Coffs Harbour City Council is in the final stage of its design and construction of a reclaimed water deep sea ocean release off Boambee Beach at Coffs Harbour. A temporary trestle was built across the beach to allow […]

read more...